The 2 floors will be divided into a total of 4 sections or phases, i.e., 2 sections or phases for each floor.
- Phase 1 is the west side of the 5th floor (the side closest to the entrance of the 5th floor) --COMPLETE
- Phase 2 is the west side of the 4th floor (the side closest to the entrance of the 4th floor) --COMPLETE
- Phase 3 is the east side of the 5th floor
- Phase 4 is the east side of the 4th floor
- During this phase the following books are unavailable:
- PQ 1482-QC 350 .O
- SB 211 .C3I57- end of Z
- All of the Juvenile section, including big books.
- F128.44.C – HA202 (5th floor)
- HG1621 – HG4928.5B (5th floor)
- During this phase the following books are unavailable:
As a result of this project, the public computers on the 4th and 5th floors will be unavailable until further notice.
Also portions of the Stacks will be unavailable as the workers move through the phases. If you need items from areas that are inaccessible, you can request them from other campuses and interlibrary loan. If you need assistance, please don't hesitate to contact us.